Other major infrastructure projects not details but were also successes are – Wexham Park Hospital – Maternity, CCU and Psychiatric main switch panel changes and cabling migrations, the Royal Marsden Hospital MRI 3 and 4 replacements, generation support and LV switch panel replacements.
Wexham Park Hospital Pharmacy Generator and LV Switchgear – £600K

M&M Technical were successful for their client in pricing and securing this major infrastructure addition to the Wexham Park Hospital HV/LV network and resilience support. The project was over two phases consisted of phase one main LV panel change and HV transformer links at £180K, and the support generator and civils works linking into the […]
St Peters Neonatal Intensive Care Unit – £748K

As part of a larger resilience project, M&M Technical, surveyed, priced and secured the major support systems project for our client. The project grew from its original proposal of a new roof top LV switch room, UPS and IPS systems, out-going dual supply distribution and major earthing provisions. The project grew to encompass the additional […]
Bankside Yards LV Installation – £220K

M&M Technical measured and priced the primary containment systems and steel fabrications supporting the containment systems, including the pre-fabricated and off-site construction of the lateral main risers, busbars systems and containment. Total tendered value £220K.
Ashford and St Peters NHS Trust – Major Resilience Project – £4.1M+

This project is for the major resilience support at St Peters Hospital to take the site to 100% essentially supported. M&M Technical attended site, surveyed the works packages and tendered the project for our client. The project included the construction of the new centralised generator farm, sheet piling and civils works and switch room construction, […]
Barts Health NHS trust – Major HV/LV Infrastructure upgrades – £2.3M

As part of the major infrastructure replacement works, M&M Technical attended site, surveyed and priced and secured phase one of these changes, consisting of the demolition and civils works and construction of the new LV switchroom, the temporary 11Kv 1Mva transformer to serve LV migrations, the replacement of 2 in nr. existing 11Kv 1Mva Transformers, […]